Search



 
Home
Columbia Basin Map
About the Author
Related WebSites
Abstracts
Catalogue
Table of Content

 

 

 

Socio-Economic Montage

COLUMBIA BASIN DEVELOPMENT PROGRAM

Strategic Review

Authored by: B.C. Hydro

Commissioned by: B.C. Hydro

January 1994

Location of Publication:
BC Hydro Library
"Columbia Basin Trust Collection"

The goal of the Columbia Basin Development Program (CBDP), as a part of meeting the future energy needs of British Columbia, is to develop specified hydroelectric resources that have an expected low environmental impact. These include the expansion of existing facilities at Brilliant, Keenleyside, Seven Mile and Waneta, and the installation of units 5 and 6 at Mica and Revelstoke. A brief description of the proposed projects includes:

Waneta Powerplant Expansion Project

The Cominco owned dam and powerplant, .5 km upstream of the confluence with the Columbia River and built in 1954, has a capacity of 375 MW. The proposed expansion would have an installed capacity of up to 380 MW. Cominco is reviewing the feasibility of upgrading the units in the existing powerplant to take advantage of a recent agreement between Cominco and the province, which gives Cominco access to additional water until the end of 2002.

Seven Mile Unit 4 

This dam and powerplant came into service in 1979-80. It is located 9.5 km upstream of the Waneta Dam and has a capacity of 608 MW. Provision for Unit 4 was made in the original design of the powerhouse.

Keenleyside Powerplant Project

Located 7 km upsteam of Castlegar and completed in 1968, the dam was built for water storage purposes and currently has no generation facilities. "Shelf ready" design of the powerplant was completed in 1992, which means that the project is advanced to a stage where site work could commence within six months of a decision to proceed with construction.

Brilliant Powerplant Expansion Project

The dam and powerplant, which are owned by Cominco, are located 3 km upstream of the confluence of the Kootenay and Columbia River. Completed in 1944, with the last unit installed in 1968, it has a capacity of 125 MW. The proposed expansion would involve the installation of two additional units with a total capacity of about 150 MW.

Revelstoke Units 5 and 6 Project

Located 5 km upstream of Revelstoke, the dam and powerplant were completed in 1984. The powerhouse has a capacity of 1843 MW and has provision for addition of a fifth and sixth unit, which would add 900 MW.

Mica Units 5 and 6 Project

Located 130 km upstream from Revelstoke Dam and completed in 1976, it comprises an earthfill dam and a 1736 MW powerhouse. It has provision to add a fifth and sixth unit, which would add 870 MW.

 

The four projects in the lower Columbia represent 7% of the forecast growth of British Columbia's electricity needs over the next two decades. Mica and Revelstoke Units 5 and 6 would be installed in response to a domestic or an export need for additional peaking capacity.

The CBDP involves the implementation of strategies and sequencing for the Columbia Basin projects that would enhance environmental, employment and economic development benefits. B.C. Hydro's objectives include utilizing its human, financial and technical resources to enhance social and economic development in the province, while being cognizant of it's primary mandate of providing reliable energy at least social cost.

This review examined three alternatives for the sequencing of the projects:

Construction of Waneta beginning in 1997, with the other Lower Columbia projects scheduled as they are economic.

Construction of Keenleyside beginning in 1995, with the other Lower Columbia projects scheduled as they are economic.

Construction of Keenleyside beginning in 1995, with other projects scheduled in order to levelize the regional workforce requirements for the development. This alternative responds to the requests of local communities in the region to schedule the projects to reduce the "boom and bust" impacts.

Each alternative was assessed in terms of meeting the above objectives and for its overall environmental, social and financial impacts upon the region and the province. They were also reviewed in light of continuing uncertainty with respect to the return of the Canadian Entitlement of the Columbia River Treaty downstream benefits, the delivery of generation from the Alcan Kemano II Completion Project, potential self-generation and wood waste projects, other possible generation projects and demand-side management programs which impact the time and choice of the lead project. It was assumed that the Canadian Entitlement to the downstream benefits is not returned to the Province. The study also included a Multiple Account Evaluation, examining various resource acquisition scenarios and determined financial, customer service, environmental, social and economic development tradeoffs.

The Review concluded that the economic and social cost premiums make the early development of the Keenleyside project unattractive. Fisheries issues (primarily pertaining to white sturgeon habitat) need to be resolved in order to retain the benefits from the Waneta expansion, the preferred option that provides the highest economic benefit. The Review also concluded that the lead times associated with Revelstoke and Mica should be reduced by completing all prerequisites for construction and thereby retain an option for a 1999 in-service date, and that additional planning studies need to be undertaken to review the future schedule of projects.

Note: Since this report was written, the following changes have taken place with respect to hydro power development in the region:

The Columbia Power Corporation, a Crown corporation wholly owned and controlled by the Province of British Columbia, was established in 1994 to own and administer hydroelectric power assets purchased by the Province in the Columbia Basin.

The signing of the Columbia Basin Accord in March 1995, resulted in a joint venture partner, the Columbia Basin Trust, for Columbia Power Corporation.

The purchase of the Brilliant dam in 1996 was the first joint venture power project investment by the two parties. In March of 1999, work began on the Keenleyside Powerplant Project, which involves the installation of a power generation facility with a capacity of 170 MW. Other projects slated for development by the joint venture partners includes:

Brilliant Redevelopment Project

Waneta Upgrades Project

Waneta Expansion Project

Thermal Power Projects

 

 
 
 

Home ] Up ] Columbia Basin Map ] About the Author ] Related WebSites ] Catalogue ] Table of Content ]

   
Living Landscapes
Royal BC Museum

Copyright © Royal BC Museum
All rights reserved

 

 

 

Terms of Use Warranty Disclaimer Copyright Privacy Statement